In my previous articles, I have talked about what you need to know about work breakdown structure for projects. In this article, I want to talk about schedule compression methods for projects. Follow me as we will look at this together in this article.

 

Schedule Compression Methods can be referred to as shortening of the project schedule without affecting the project scope. Setbacks or revised deadline can cause production problems, in which there is a little time to do a lot of work. When these issues occurs , product quality is often sacrificed.

 


Schedule Compression alleviates the pressure of completing too many activities in a short time without negatively affecting the project scope .

 

Compression may be achieved in one of two ways : Fastracking and crashing.

Schedule Compression Methods for projects

Typical example…

A carpenter and his subcontractor are building and then installing cabinets in a new housing development. The realty company has a higher demand than expected and asks the carpenter to move up his finish date by three weeks.

 

In order to meet his deadline , the carpenter decides to change the order of assignments for the remaining company work. He tells the subcontractor to work on the installation of the cabinets whole he finishes building the cabinets.

 

This changes the Precedence . Instead of building all the cabinets and then installing them , the installation is able to start before the building of the cabinets is complete as in the original schedule.

 

READ THIS  How To Determine Stakeholder Needs For Projects

Due to the increase in production, the carpenter finishes the work a week ahead of the schedule rather than three weeks behind.

 

READ THIS  VIDEOS: How Project Can Enable Value Creation

#1 Fast-Tracking

Fast tracking is the process of compressing the project duration by performing some activities concurrently that were originally scheduled sequentially.

 

Typically, fast tracking involves identifying FS relationships that could be done in parallel , either as Finish to finish ,Start to finish , or Start to start relationships, or by simply adding some leads to FS activities.

 

Some fast tracking may entail looking very creativity at the network diagram to see if some discretionary dependencies could be done completely independently. usually ,no added costs are incurred from fast tracking; however it can result in increased risk and rework.

 

Typical example…

Sponsors are pressuring Carol to bring a new product to market quickly. Carol decides to fast track some activities a lead leadership between the development of the new product and the writing of the associated user manual. The total duration of the two activities in shortened , because writing the manual can start before the product development is complete. Consequently , the project duration is shortened.

 

Crashing

Crashing is a schedule compression method that analyses cost and schedule trade Offa to determine how to obtain the great schedule compression for the least incremental cost. crashing typical involves allocating more resources to activities on the critical path in an effort to shorten the duration , thereby increasing project costs.

 

To crash a schedule, analyse:

 

  • Duration estimates under normal conditions
  • Cost associated with the normal conditions
  • Duration estimates under the crash condition.
  • Cost associated with crash condition
READ THIS  Understanding Organisation's Culture Influence On Projects

 

The formula for calculating crash coats per week is (crash coat – normal coat) / ( normal time – crash time ).

 

Example…

As project manager for the company website project, you are.asked to compress the schedule for the design deliverable. There are eleven activities , five of which are on the critical path. Using the formula (crash coat – manual cost) / ( normal time- crash time ) , you calculate the crash coats per week for each of the five activities to determine which activities will provide the greatest duration reduction for the least incremental coat. Your calculations are :

READ THIS  How To Develop A Work Breakdown Structure For Projects

 

Crashing

 

 

 

 

 

 

 

 

 

While you have not yet analysed the effect of crashing the activities , you can determine from your calculations that:

  • Activity D has a net gain of three weeks at a cost of just $500 per week.
  • Activity C reduces the schedule by two weeks at a cost of only $1,500 per week.
  • Activity E is another possible candidate with theee-week reduction at a cost of $2,000 per week.
  • Activity B , which has a crash coat of $4,500 per week and a reduction of only one week, is the worst candidate for crashing.
  • The order in which the activities should be crashed in D,C,E,A, and B.
  • The total number of weeks by which the project could be shortened if all of the activities on the critical path are crashed is 11 (45-34).
  • The total additional cost if all activities on the critical path are crashed is $23,000 ($71,000-$48,000).

 

 

 

 

Now your take on this article…

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.

Become Part Of our Fan Base on Facebook. Click Here.

Follow Us on Twitter. Click Here.

Download Our App. Click Here
Many Crypto. One place. Use Roqqu

READ THIS  How To Develop A Work Breakdown Structure For Projects

 

 

Adeniyi Salauhttps://cehnigeria.com
I am an IT entusiast and a man of many parts. I am a Certified Digital Marketer, Project Manager and a Real Estate Consultant. I love writing because that what keeps me going. I am running this blog to share what I know with others.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

CommentLuv badge

Most Popular

Creating Value Proposition For Digital Channels

How To Create Value Proposition For Digital Channels     None of the previous channels would be relevant in a digital marketing strategy without a strong message...

8 Types OF Digital Channels In Digital Marketing

8 Types OF Digital Channels In Digital Marketing     When thinking through your digital marketing strategy, beyond the message and the creative, you need to know...

Who Is a Community Manager and What Does It Do?

Who Is a Community Manager and What Does It Do?   Have you ever wondered what a community manager is? What do you work on? What...

How Cryptocurrencies Are Changing The Sport Industry?

  How Cryptocurrencies Are Changing The Sport Industry?   Cryptocurrency is changing the rules in every sector and industry. Bitcoin and other tokens have become powerful tools...