4 Types Of Schedule Network Analysis

4 Types Of Schedule Network Analysis

 

 

In my previous article, I have looked at some of the facts that you need to know about the different standard Diagramming notation for projects. In this article , I want to talk about four types of Schedule Network Analysis for projects. Follow me as we will look at that together in this article.

 

Schedule Network Analysis is a technique that is used to calculate that is used to calculate the theoretical early and late start and finish dates for all project activities. In other words , it helps create a project schedule.

 

This method also generates float or slack.

 

Schedule Network Analyst s may be achieved using one of the four methods.

  • Critical Path Method
  • Critical Chain Method
  • What-if scenerio
  • Resource leveling

Typical example…

You are trying to craft a schedule for the creation of a new marketing campaign, which will involve finding a new advertising agency, creating the advertisements , and producing marketing materials.

Schedule Network Analysis

Because the project contains so many different work packages , you decide that schedule network analysis is neccesary.

 

Using a project management software application. , you are able to define the network path from “request for proposals” to “launch campaign”.

 

From there ,you can estimate the points in the schedule where there is slack and adjust the activities accordingly.

 

READ THIS  How To Create A Schedule Baseline For

#1 Critical path method

The Critical Path Method is a network analysis method that uses a sequential finish to start network logic and calculates one early and late start and finish date for each activity using a single-duration estimate.

 

READ THIS  3 Major Schedule Formats For Projects

The longest path through the network- the critical path- is defined. Then float is calculated to identify activities where there is some scheduling flexibility.

 

Critical Path Method is the mathematical analysis technique used in most type of project management software.

 

# Critical chain method

The critical Chain Method is a network analysis method that allows you to consider resource limitations and adjust the schedule as appropriate to work within those limitations . The critical Chain is established by analysing the critical path alongside the resources that are actually available.

 

The critical Chain Method is also used to plan and manage reserves or buffers and helps mitigate possible coat and schedule risks.

 

#3 What if Scenario analysis

The what-id scenario analysis method allows you to consider different situations that may occur and influence the schedule; it assesses the feasibility of the schedule under various adverse conditions.

 

It allows you to compute different schedules based on potential delays or unplanned events that are a normal part of business life, such as key employees’ resigning during a project.

 

The outcome are also used to mitigate the impact of unexpected situations when preparing risk response plans. The method helps in selecting the optimum plan.

 

Typical example…

The project manager , David  used the what-if scenario analysis method to compute different schedules for a planned move of the corporate headquarters to a new facility.

READ THIS  How To Develop A Project Schedule For Projects

 

He based how computations on several scenarios such as : What if the contractor for the new building brings the goods in late? What if key decisions makers are allocated elsewhere during the planning process ? What if there is a union strike affecting the construction workers ?

READ THIS  Understanding Phase Gate Reviews For project

 

 

 

 

Now your take on this article…

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.

 

 

Become Part Of our Fan Base on Facebook. Click Here.

Follow Us on twitter. Click Here.

Download Our App. Click Here
Many Crypto. One place. Use Roqqu

 

 

 

 

Adeniyi Salauhttps://cehnigeria.com
I am an IT entusiast and a man of many parts. I am a Certified Digital Marketer, Project Manager and a Real Estate Consultant. I love writing because that what keeps me going. I am running this blog to share what I know with others.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

CommentLuv badge

Most Popular

Common Mistakes You Are Making in PPC Campaigns

Common Mistakes You Are Making in PPC Campaigns   Pay-Per-Click (PPC) is a type of marketing that falls under online advertising. Here, advertisers accrue costs when...

Highlighting Major Components Of Website Design

Highlighting Major Components Of Website Design     There are many people that have come up with their own ideas of what they feel it's important when...

5 Steps To Deploy A Successful Content Marketing Strategy

5 Steps To Deploy A Successful Content Marketing Strategy   A customer-centric content marketing strategy delivers qualitative content to meet the needs of consumers who educate...

Differences Between Website Optimization And SEO

Differences Between Website Optimization And SEO       Website optimization: deals more with the user experience and making the website easier to use. Examples include website layout,...