6 Terms Relating To Schedule Management For Projects2 min read

Schedule Management plan

6 Terms Relating To Schedule Management For Projects

 

 

In my previous article, I have talked about Standard Schedule Diagramming Notations for projects. In this article, I want to talk about six terms relating to schedule management for projects. Follow me as we will look at these terms together in this article.

 

#1 The Critical Path

The critical path is the network path that has the longest duration. Activities on the critical path cannot be displayed or the whole project will be delayed unless subsequent activities are shortened.

 

The critical path is calculated by doing a forward pass to calculate the Early Start and Early Finish for each activity and then a backward pass to calculate the Late Start and Late Finish for each activity . The path with the longest duration and no scheduling flexibility is the critical path.

Schedule Management for projects

#2 Float

Float is the amount of time an activity can be delayed from it’s Early Start without delaying the project finish date or the consecutive activities . Float occurs only in activities that are not on the critical path. Float is also called slack. There are two types of floats;Total and Free.

 

#3 Total Float

Total float is a type of float where the total amount of time an activity requires can be delayed without delaying the project finish date. Total float for an activity can be calculated by subtracting it’s Early Finish from.its Late Finish or it’s Early Start from it’s Late Finish.

 

READ THIS  Understanding Progressive Elaboration For Projects

Please note that when you see the term float by itself, it generally refer to total float.

 

#4 Free Float

Free float is the amount of time an activity can be delayed without delaying the Early Start of any activity that immediately follows it. It allows flexibility of the start or finish time within the activity only.

 

If there is a strong of activities with float, free float will be available only at the end of the string.

 

Free Float for an activity is calculated by subtracting the Early Finish of the activity from the Early Start of it’s successor activity.

 

Now your take on this article…

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.

 

 

Become Part Of our Fan Base on Facebook. Click Here.

Follow Us on twitter. Click Here.

Download Our App. Click Here
Many Crypto. One place. Use Roqqu

 

 

 

About Adeniyi Salau 613 Articles
I am an IT enthusiast and a man of many parts. I am a Certified Digital Marketer, Project Manager and a Real Estate Consultant. I love writing because that's what keeps me going. I am running this blog to share what I know with others. I am also a Superlife Stem Cell Distributor. Our Stem Cell Products can cure many ailments.

2 Comments

Leave a Reply

Your email address will not be published.


*


CommentLuv badge