How To Create Activity Lists For Projects

Activity list for projects

How To Create Activity Lists For Projects

 

In my previous article, I have talked about some of the facts that you need to know about.milestone and milestone lists for projects. In this article, I want to talk about some of the steps to follow when you need to create activity lists for projects. Follow me as we will look at that together in this article.

 

Accurately defining project activities ensures that all project activities are tied to the project scope, which will mitigate the potentially damaging effects of scope creep. Scope creep happens when more features are added to the project without a proportionate increase in the cost and scope of the project.

 

To define activities and create an activity list, follow these guidelines:

 

#1 Gather inputs

There is a need for you to gather all the resources that you need to create the activity list. Some of these resources may include : the WBS, activity list template, the scope statement , scope baseline , relevant historical information, as well as constraints and assumptions for the project.

 

#2 Decomposition

You also need to analyse and decompose each work package of the WBS into activities that will be required to produce the deliverables.

 

You have to conduct brainstorming sessions with the project team to ensure that no required activities are overlooked.

Activity list for projects

You have to conduct the scope statement to ensure that activities will enable you to meet the project objectives.

 

You have to ensure that you conduct progressive elaboration for work packages that cannot be defined as the project starts. That is, create detailed activities for short term WBS work packages.

 

#3 Consult records

There is a need for you to consult records of similar projects to identify possible activities. Consulting such similar projects will allow you to know what you need to do in order to have a perfect projects.

 

#4 Consult SME

There is a need for you to consult Subject Matter Experts to get their expert opinions about the project. They will have an independent assessment of the project and plan along with all other stakeholders in order to have a project that can stand the test of time.

 

#5 Evaluate constraints

Moreso, there is a need for you to evaluate assumptions and constraints that have been identified for the project in order to know their possible impacts on activity definition for the project.

 

#6 Evaluate your activity list

Once you have decomposed each work package into activities , evaluate your activity list:

You need to ensure that the description accurately reflect the action to be performed.

 

You also need to verify that the activity descriptions are as specific as possible. For example, if the desired outcome is a revised user manual, describe the activity as ” revise user manal” rather than ” produce new user manual”.

 

You need to confirm that the activities listed for each work package are neccesary and sufficient for satisfactory completion of the deliverable.

 

Also, you have to verify that the list is organised as an extension of the WBS.

 

#7 Create Activity attributes

There is a red for you to create activity attributes for each activity in the activity list by determining responsible team members and the level of the effort required to achieve project objectives.

 

#8 Define the milestones

There is a need for you to define the milestones in the project and create a milestone list. This will allow you to know whether your you project is running late or not. It will also allow you to bring your project back on track.

 

Typical example…

A project team for a web design company used the WBS and activity list from a previous, similar project to create an activity list for their initial designs work package. The team used historical records of the previous project to help identify activities that may be required to complete the deliverable.

 

Depending on the activities they select, the length of time maybe lenghtened or shortened.

 

Additionally, an outside multimedia expert was consulted about activity identification . Finally, to make sure that the activities supported the project objectives, the team reviewed the scope statement.

 

The project team gathered inputs and resource materials to create the activity and milestone lists and activity attributes for the work package.

Now your take on this article…

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.

 

 

Become Part Of our Fan Base on Facebook. Click Here.

Follow Us on twitter. Click Here.

Download Our App. Click Here
Many Crypto. One place. Use Roqqu

 

 

About Adeniyi Salau 788 Articles
I am an IT enthusiast and a man of many parts. I am a Certified Digital Marketer, Project Manager and a Real Estate Consultant. I love writing because that's what keeps me going. I am running this blog to share what I know with others. I am also a Superlife Stem Cell Distributor. Our Stem Cell Products can cure many ailments.

Be the first to comment