How To Identify Critical Path For Projects

How To Identify The Critical Path For Projects

 

 

Sometimes, the resources you are counting on may not be available when they are scheduled to be. How do you know when your project cannot be successfully completed? The answer is that you must identify the critical path when developing the project schedule. In this article, I want to talk about how to identify the critical path for projects.

 

Identifying the critical path allows you to determine which activities have scheduling flexibility before you complete your project schedule.

Identify critical path for projects

Critical activities 

Critical activities are the activities that are on the critical path. Generally, for all activities along the critical path, ES=LS and ES=LF. There can be no flexibility in the start time or the finish time for these activities. Activities that are not on the critical path usually have some flexibility in their start and finish dates.

 

How to identify the critical path…

To identify the critical path for a project with FS precedence relationships: 

 

#1 Conduct Forward Pass

You need to conduct a forward pass to determine the ES and EF for each activity:

  • Use zero for the first activity’s ES.
  • Enter the first activity’s duration as it’s EF.
  • Calculate the ES for each successor activity when using the largest EF from any of its predecessor activities plus or minus any leads or lags. 
  • Calculate the EF for each successor activity by adding its duration to it’s ES.
  • Move through all the activities until you have an ES and EF for each one. 

 

READ THIS  4 Types Of Project Prototyping Models
READ THIS  Analysing Program And Portfolio Management For Projects

#2 Backward pass

You need to perform a backward. pass to determine the LS and LF for each activity.

  • Enter the last activity’s EF as it’s LF time.
  • Subtract the last activity’s duration from its EG to determine it’s LS.
  • Calculate the LF for each predecessor activity using the earliest LS from any of its successor activities plan or minus any leads or lags.
  • Calculate the LS for each activity by subtracting its the duration from it’s LF.
  • Move backwards through all activities until you have the LF and LS for each one.

 

#3 Calculate float

Calculate float:

  • For each activity, subtract it’s EF from it’s LF to determine total float.
  • For each string of activities with float, calculate free float for the last activity in the string by subtracting it’s EF from its successor activity ES.

 

#4 Identify Critical path

You need to identify the critical path as the path with the longest duration and zero float.

Critical path method

Other factors…

  • The ES for the first activity is 0.
  • The EF for the first activity in its ES plus its duration.
  • The ES of all successor activities is the latest EF of any of its predecessor activities plus or minus any leads or lags between the two activities.
  • The EF or all subsequent activities is it’s ES plus its duration.
  • The LF for the last activity is the same as it’s EF time.
  • The LS for the last activity is its EF minus its duration.
  • The LF for any predecessor activity is the same as the earliest LS of any of its successors plus or minus any leads or lags between the two activities.
  • The LS of any predecessor activity is it’s LF minus its duration.
  • Only the three activities that are not on the critical path.
  • Only the last activity in the last string has free float.
  • The critical path is indicated by bold lines with arrows and includes activities along the path.
READ THIS  Infographics: How To Lock Out Unwanted Guests In Windows 7
READ THIS  How Projects Can Enable Business Value Creation

 

 

Now your take on this article…

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.

Become Part Of our Fan Base on Facebook. Click Here.

Follow Us on Twitter. Click Here.

Download Our App. Click Here
Many Crypto. One place. Use Roqqu

 

Adeniyi Salauhttps://cehnigeria.com
I am an IT entusiast and a man of many parts. I am a Certified Digital Marketer, Project Manager and a Real Estate Consultant. I love writing because that what keeps me going. I am running this blog to share what I know with others.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

CommentLuv badge

Most Popular

Highlighting Major Components Of Website Design

Highlighting Major Components Of Website Design   There are many people that have come up with their own ideas of what they feel it's important when...

5 Steps To Deploy A Successful Content Marketing Strategy

5 Steps To Deploy A Successful Content Marketing Strategy   A customer-centric content marketing strategy delivers qualitative content to meet the needs of consumers who educate...

Differences Between Website Optimization And SEO

Differences Between Website Optimization And SEO       Website optimization: deals more with the user experience and making the website easier to use. Examples include website layout,...

The ULTIMATE On-Page SEO Plugin for WordPress

The ULTIMATE On-Page SEO Plugin for WordPress     When you do, you’ll receive over $500 worth of premium WordPress themes (with updates!), plus a whole lot...