In my previous article, I have talked about all that you need to know about work breakdown structure for projects. In this article I want to talk about Standard Schedule Diagramming Notations  for projects. Follow as we will look at them together in this article.

 

Now the notations…

#1 Early Start

This denotes the earliest time an activity can start. usually, the ES of the first activity in a network diagram is zero. The Early Start of all other activity in the latest Early Finish of any predecessor activities. 

 

#2 Early Finish 

This denotes Early Finish. The earliest time an activity can finish. The EF for the first activity is the same as it’s duration . For all other activities ,EF is the latest EF of all the predecessor activities of an activity plan it’s duration. 

Standard schedule Diagramming notations

#3 Late Finish

This denotes Late Finish. It is the latest time an activity can finish. The late Finish for the activity is the same as its Early Finish time. The LF for any predecessor activity is the earliest Late Start of any of it’s successor activity.

 

Late Start

This is the latest time an activity can start. The LS for the last activity is it’s Early Finish minus its duration. The Late Start for any predecessor activity is it’s Late Finish minus it’s duration.

 

Duration

This is the number of work periods required for the completion of an activity.

 

 

Now your take on this article…

I know you might agree with some of the points that I have raised in this article. You might not agree with some of the issues raised. Let me know your views about the topic discussed. We will appreciate it if you can drop your comment. Thanks in anticipation.

 

 

Become Part Of our Fan Base on Facebook. Click Here. 

Follow Us on twitter. Click Here.

Download Our App. Click Here
Many Crypto. One place. Use Roqqu

 

 

 

About Adeniyi Salau 829 Articles
I am an IT enthusiast and a man of many parts. I am a Certified Digital Marketer, Project Manager and a Real Estate Consultant. I love writing because that's what keeps me going. I am running this blog to share what I know with others. I am also a Superlife Stem Cell Distributor. Our Stem Cell Products can cure many ailments.

Be the first to comment

Leave a Reply

Your email address will not be published.


*


CommentLuv badge